Power Assure Case Studies
A10 Networks
Extending the Life of a Data Center wth Power and Cooling Efficiencies To help accommodate the company's rapid growth, A10 Networks needed better visibility and control of power utilization throughout its data center. Power Assure's EM/4 software provided just the Data Center Infrastructure Management platform A10 Networks needed to integrate monitoring, analysis and automation in a single, intuitive system. Accenture
Sun Microsystems hosted demonstrations of Power Assure's Dynamic Power Management and Optimization capabilities. After measuring the precise draw of Sun servers at off, idle, and 100% load, Power Assure's capacity planning functionality accurately predicted capacity in the racks, without the inaccuracies of estimates based on vendor power labels. This accuracy enables Power Assure to plan IT power needs exactly.
This case study was published by Accenture Technology Labs.
Cytak
Energy Efficient Data Center Demonstration Project
The application utilization for larger server farms in today's data centers is typically highly volatile due to many factors. Time-of-day usage patterns, promotions and advertisements, and unexpected events all cause spikes in demand, both planned and unplanned. As a result, data center operators have to deal with a high level of uncertainty when planning capacity. They mitigate the risk of a service outage by over-provisioning equipment and keeping their entire pool of servers up and running.
This case study used Power Assure's Dynamic Power Optimization to adjust server capacity to meet actual application loads. The results confirmed the estimated gains in efficiency, without impacting customer service levels despite real-life, highly volatile usage patterns. This case study underscores the advantages of moving data centers to an energy-proportional model.
This case study was published by Silicon Valley Leadership Group. |